Roadway work continues along the east side of Nippersink Blvd.

The weather this week hampered the contractor’s production this week, but they still completed placing the new aggregate base for the roadway and sidewalk and they framed and poured the new street light foundations along the east side of Nippersink Boulevard.

Next week, weather permitting, the contractor plans to complete the new concrete sidewalk and pave the first layer of new asphalt along the east side of Nippersink Boulevard. They also anticipate completing the remaining work for the new street light controller.

Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please refrain from cell phone use and be alert when traveling through the work zones.

Framing for new curb & gutter along Nippersink Blvd.

The contractors completed excavating and placing new aggregate base for the roadway and they framed and poured the new curb & gutter along the east side of Nippersink Boulevard.

Next week, weather permitting, the contractor plans to complete the new concrete sidewalk and pave the first layer of new asphalt along the east side of Nippersink Boulevard. They also anticipate completing the remaining work for the new street light foundations.

Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please refrain from cell phone use and be alert when traveling through the work zones.

Concrete pours are complete for the new Nippersink Blvd. retaining wall

The contractors completed the installation of numerous reinforcement bars, and then they framed and poured concrete for the remaining sections of the new retaining wall along the east side of Nippersink Boulevard.

Next week, weather permitting, the contractor plans to remove the framing on the remainder of the retaining wall and continue the remaining sidewalk along the east side of Nippersink Boulevard. They also anticipate completing the remaining work at the Metra Station.

Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please refrain from cell phone use and be alert when traveling through the work zones.

Pouring the first sections of the Nippersink Blvd. retaining wall

The contractors completed the installation of numerous reinforcement bars, and then they framed and poured concrete for sections of the new retaining wall along the east side of Nippersink Boulevard.

Next week, weather permitting, the contractor plans to complete the framing and the concrete pouring on the remainder of the retaining wall. They also anticipate completing the asphalt work at the Metra Station.

Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard.  Please be aware of construction workers and equipment when traveling through the work zone.