The contractors continued the storm sewer installation along the east side of Nippersink Boulevard north of Grand Avenue, and they also completed paving the first layer of new asphalt pavement along the west side of Nippersink Boulevard near Grand Avenue.
Once the paving was complete, the contractor established a new traffic pattern (Stage 2) with traffic modified to one-way southbound along the west side of Nippersink Boulevard between Grand Avenue and Oak Street.
Next week, weather permitting, the contractor plans to complete the proposed storm sewer installation on the east side of Nippersink Boulevard, complete an asphalt pavement patch on Grand Avenue, and to begin preparation work for the construction of the new retaining wall on the east side of Nippersink Boulevard.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.