The contractor completed the excavation and installation of the new aggregate base for the roadway improvements along the west side of Nippersink Boulevard this week. They also completed framing and pouring the new concrete curb & gutter along the west side of Nippersink Boulevard.
Next week, weather permitting, the contractor plans to continue the proposed storm sewer installation in locations on the east side of Nippersink Boulevard, and possibly pave the first layer of the new asphalt pavement along the west side of Nippersink Boulevard.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.