The contractors continued the sidewalk installation at the northwest and northeast corners of Nippersink Boulevard and Grand Avenue as well as the southeast corner of Rolland Place and Nippersink Boulevard. They also continued excavation work and installing the underdrain for the new retaining wall on the east side of Nippersink Boulevard.
Next week, weather permitting, the contractor plans to complete the remaining sidewalk sections at Nippersink Boulevard and Grand Avenue. They also plan to continue work on the new retaining wall on the east side of Nippersink Boulevard.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.