The contractors continued work on the new retaining wall on the east side of Nippersink Boulevard by welding connecters and brackets on the previously installed piling. They also completed removing the existing curb & gutter and concrete sidewalk and began framing for the new work at the southwest corner of Nippersink Boulevard and Grand Avenue.
Next week, weather permitting, the contractor plans to pour the curb & gutter and sidewalk sections at the southwest corner of Nippersink Boulevard and Grand Avenue. They also plan to continue work on the new retaining wall on the east side of Nippersink Boulevard.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please refrain from cell phone use and be alert when traveling through the work zones.