The contractors continued work on the new retaining wall on the east side of Nippersink Boulevard by drilling tie back anchors and welding brackets to connect the anchors to the piling previously installed.
Next week, weather permitting, the contractor plans to continue work on the new retaining wall on the east side of Nippersink Boulevard, and possibly begin some improvements at the Metra Station.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.