The contractors continued the storm sewer installation along the east side of Nippersink Boulevard north of the existing retaining wall, and they completed an asphalt pavement patch on Grand Avenue.
Next week, weather permitting, the contractor plans to continue the proposed roadway excavation and possibly frame and pour the proposed curb & gutter along a portion of the east side of Nippersink Boulevard, and to continue preparation work for the construction of the new retaining wall on the east side of Nippersink Boulevard.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.