Roadway improvements continue along the east side of Nippersink Blvd.

Last week, the contractor completed the proposed roadway excavation, installed the new aggregate roadway base, and installed the proposed underdrain system along the east side of Nippersink Boulevard from Oak Street to the retaining wall.

This week, weather permitting, the contractor plans to:

  • Remove the existing pavement and begin the proposed roadway excavation along a portion of the east side of Nippersink Boulevard between Grand Avenue and Ernest Avenue.
  • Frame and pour the proposed curb & gutter along the east side of Nippersink Boulevard from Oak Street to the retaining wall.
  • Continue preparation work for the construction of the new retaining wall on the east side of Nippersink Boulevard.

Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.