The contractor completed the removal of the existing pavement and sidewalk, completed the proposed roadway excavation, and began installing the new aggregate roadway base along a portion of the east side of Nippersink Boulevard between Grand Avenue and Ernest Avenue. They also framed and poured the proposed curb & gutter along the east side of Nippersink Boulevard from Oak Street to the retaining wall.
Next week, weather permitting, the contractor plans to complete the installation of the new roadway aggregate base and also frame and pour the proposed curb & gutter along a portion of the east side of Nippersink Boulevard between Grand Avenue and Ernest Avenue.
Motorists should expect minor delays as the roadway work progresses along Nippersink Boulevard. Please be aware of construction workers and equipment when traveling through the work zone.